Odisha · 2022

LNG storage tank, circumferential prestress

Horizontal and vertical prestress to a 165,000 m³ full-containment outer tank, cast against self-climbing formwork.

Tank capacity
165,000 m³
Wall height
38.5 m
Horizontal tendons
312
Strand installed
640 t
SECTION A–AASPAN 45 000e = 1 420P = 4 480 kN19 × 15.7 mm STRAND · 1 860 MPaDEVIATORDEVIATORLIVE ENDLIVE ENDELONGATION CALCULATED PER TENDON, MEASURED PER END, SIGNED ON THE DAYDUCTS PRESSURE-TESTED BEFORE CONCRETE · VACUUM-ASSISTED GROUTINGIRC:18 / IS 1343EN 10138 STRAND
FIG. 01Post-tensioned box girder — tendon profile and support sectionELEVATION · NTS

Scope of supply

  • Circumferential and vertical post-tensioning
  • Self-climbing wall formwork, 24 units
  • Vacuum grouting with recorded pressures
  • Stressing records and third-party witness

Divisions involved

01

The problem

A full-containment tank wall has no tolerance for a tendon that will not stress to its calculated elongation, and the buttress arrangement meant every horizontal tendon turned through 240 degrees with high friction losses. The client required third-party witness on every stressing operation.

02

What we did

Friction was measured on site with a lift-off test on the first three tendons of each level and the calculation recalibrated to the measured coefficients before the rest were stressed. Formwork climbed on 24 self-climbing units so the wall progressed on a continuous 4.5 m lift cycle independent of crane time. Grouting was vacuum-assisted with pressure and volume logged per tendon.

03

What happened

All 312 horizontal tendons stressed within the ±5 % elongation band at first attempt. Wall completed in 32 lifts with no crane-driven delay to the stressing programme.

Measured outcome

165,000 m³
Tank capacity
38.5 m
Wall height
312
Horizontal tendons
640 t
Strand installed
08Next step

Send us a span table.

Give us the general arrangement and the programme. You will get two or three viable erection methods back, each with a cycle time we are prepared to stand behind — before anyone talks about price.