Skip to content
IBEC — Innovative Construction Solutions
Telangana · 2024

Elevated metro corridor, precast segmental viaduct

Two overhead launching gantries erecting 11.6 km of segmental deck over a live six-lane arterial road, on a three-day span cycle.

Viaduct length
11.6 km
Typical span
31 m
Segments erected
2,840
Cycle achieved
3.0 days
SPAN 31 00018 500P1P2P3LAUNCH →1Main truss girder2Winch trolley3Segment being placed4Main support leg on pier5Launching nose1 MAIN TRUSS GIRDER2 WINCH TROLLEY3 SEGMENT BEING PLACED4 SUPPORT LEG5 LAUNCHING NOSE
FIG. 01Overhead launching gantry — span-by-span erection, mid-cycleELEVATION · NTS

Scope of supply

  • Two overhead launching gantries, 640 t each
  • Segment lifters and yard handling equipment
  • Bonded internal post-tensioning, 12 and 19 strand
  • Erection supervision for the full corridor

Divisions involved

01

The problem

The alignment ran the length of an arterial road that could not be closed, with three signalised junctions inside the corridor and a minimum radius of 195 m through the tightest of them. Traffic management allowed a working window of six hours a night at the junctions and nothing at all during the day. A conventional ground-supported method was never viable, and the contractor had no yard within 40 km of the far end of the corridor.

02

What we did

Two overhead gantries were designed to work towards each other from opposite ends, each carrying its own segment feed from behind so that no delivery ever entered the live carriageway. The gantry main girders were sized for the 195 m radius by splitting the front support into an articulated pair, which let the machine steer through the curve without unloading a pier. Post-tensioning was detailed alongside the erection scheme so the stressing sequence never held up a launch.

03

What happened

The corridor was erected at a sustained three-day cycle per span with a best week of five spans across the two machines. No lane closure was taken outside the agreed night windows and the segment yard operated at eleven segments a day against a planned nine.

Measured outcome

11.6 km
Viaduct length
31 m
Typical span
2,840
Segments erected
3.0 days
Cycle achieved
08Next step

Send us a span table.

Give us the general arrangement and the programme. You will get two or three viable erection methods back, each with a cycle time we are prepared to stand behind — before anyone talks about price.

Projects & tenders
projects@ibec.co.in
Response
An engineer reads every enquiry. Expect a technical reply within two working days, not a brochure.