Assam · 2023

Six-lane river crossing, balanced cantilever

Four pairs of form travellers building a variable-depth box girder across a braided river with a five-month working season.

Main span
160 m
Deck depth
9.5 – 3.5 m
Travellers
8 (4 pairs)
Segment cycle
6 days
SPAN 31 00018 500P1P2P3LAUNCH →1Main truss girder2Winch trolley3Segment being placed4Main support leg on pier5Launching nose1 MAIN TRUSS GIRDER2 WINCH TROLLEY3 SEGMENT BEING PLACED4 SUPPORT LEG5 LAUNCHING NOSE
FIG. 01Overhead launching gantry — span-by-span erection, mid-cycleELEVATION · NTS

Scope of supply

  • Eight form travellers, 220 t capacity
  • Pier head brackets and stability towers
  • Internal and external post-tensioning
  • Geometry control and camber monitoring

Divisions involved

01

The problem

The river carries its full discharge for seven months of the year and the piers stand in the active channel. Everything above pier cap level had to be built from the deck, in a season that closes without warning. A single traveller pair per pier would not have finished the cantilevers before the water returned.

02

What we did

Four pairs of travellers were built and commissioned before the season opened so all four piers could cantilever simultaneously. Each traveller was designed around a 6-day cycle rather than the more usual 7, by moving the rebar cage assembly off the traveller and onto a deck-level jig. Geometry was controlled against a daily survey with temperature-corrected camber targets issued each morning.

03

What happened

All four cantilevers closed within the season. Measured closure error at the mid-span joints was within 14 mm vertically and 6 mm horizontally against a permitted 25 mm.

Measured outcome

160 m
Main span
9.5 – 3.5 m
Deck depth
8 (4 pairs)
Travellers
6 days
Segment cycle
08Next step

Send us a span table.

Give us the general arrangement and the programme. You will get two or three viable erection methods back, each with a cycle time we are prepared to stand behind — before anyone talks about price.

Projects & tenders
projects@ibec.co.in
Response
An engineer reads every enquiry. Expect a technical reply within two working days, not a brochure.